Inkai
- Inkai is owned 40% by Cameco and 60% by Kazatomprom, which is majority-owned by the Kazakh government.
- Tapping into the vast uranium potential of Kazakhstan, Joint Venture Inkai LLP operates the in situ recovery mine.
- The ISO 14001 and BSI OHSAS 18001 certified facility follows western standards for worker safety and environmental protection since it began operations in 2008.
- Inkai has produced 106.4 million packaged pounds from 2009 to 2025.
Production
2026 Q1 Update
- Production
Production on a 100% basis was 2.5 million pounds for the quarter, compared to 1.1 million pounds in the same period last year due to the unplanned suspension of production for several weeks in January 2025.
JV Inkai is targeting 2026 production of 10.4 million pounds (100% basis) of which our purchase allocation is expected to be 4.2 million pounds. The achievement of JV Inkai’s 2026 production target requires it to successfully manage several ongoing risks, including the availability of sulfuric acid, other procurement and supply chain issues, transportation challenges, construction delays and inflationary pressures on its production costs.
Due to equity accounting, our share of production is shown as a purchase at a 5% discount to the spot price and included in inventory at this value at the time of delivery. Our share of the profits earned by JV Inkai on the sale of its production to the joint venture partners is included in “share of earnings from equity-accounted investee” on our consolidated statement of earnings. Excess cash, net of working capital requirements, is distributed to the partners as dividends once declared.
The geopolitical situation continues to cause transportation risks in the region. We could continue to experience delays in our expected Inkai deliveries. To mitigate this risk, we have inventory, long-term purchase agreements and loan arrangements in place we can utilize. Depending on when we receive shipments of our share of Inkai’s production, our share of earnings from this equity-accounted investee and the timing of the receipt of our share of dividends from the joint venture may be impacted.
- Delivery Schedule
The geopolitical situation continues to cause transportation risks in the region. We could continue to experience delays in our expected Inkai deliveries. To mitigate this risk, we have inventory, long-term purchase agreements and loan arrangements in place we can draw on. Depending on when we receive shipments of our share of Inkai’s production, our share of earnings from this equity-accounted investee and the timing of the receipt of our share of dividends from the joint venture may be impacted.
Environment & Safety
Worker safety, environmental monitoring and proper decommissioning after project completion are of the utmost importance to Cameco.
Reserves & Resources
Our mineral reserves and resources are the foundation of our company and fundamental to our success.