
Home: About Cameco Port Hope: Q&As
Cameco has suspended uranium hexafluoride (UF6) production until the company and its independent experts (Golder Associates) can complete a detailed, methodical assessment of the situation and develop the most appropriate long-term environmental management plan.
Production of uranium dioxide (UO2) and other activities at the conversion facility are continuing.
The most likely source of contamination to the soil and ground water beneath building 50 is through leaks in joints in the concrete on the ground floor of the building. All in-ground structures such as floor trenches, sumps and pits were thoroughly cleaned to facility their inspection.
As of September 24, Cameco and its consultants have confirmed the existence of two leak points near the original excavation area. Both identified leak points are in joints between walls and trenches. There are two other trenches in the area that have cracks that are suspected leak points
The plant has been shut down and Cameco has stopped generating production-related process effluent. Therefore, the leak paths from the two identified areas have been stopped. Other potential leak paths are being inspected.
By suspending UF6 production, Cameco's consultants can conduct a thorough inspection of all tanks, trenches and sumps. Suspending operations also safeguards against the possibility of making the contamination worse.
Initial sampling of soil and groundwater focused on uranium and chemicals that are part of the UF6 production process. Testing has confirmed the presence of uranium, potassium, arsenic and fluorides in the soil and groundwater beneath the UF6 plant.
Golder Associates, the hydrogeological consultants retained by Cameco to provide expert advice, has been taking ongoing samples from wells and submitting these samples to an external lab to analyze for metals, radium and major ions. This will include new and existing wells located outside the UF6 plant, as well as new test wells within the plant.
Results taken over the past several weeks from the eight monitoring wells surrounding the plant raise no concerns because they are consistent with historical measurements.
Cameco must provide the CNSC with 24 hours notice of its intent to resume production. Written approval from the CNSC will be required before Cameco can resume UF6 production.
Cameco has been providing daily updates to the CNSC, the Ontario Ministry of Environment and the Ganaraska Region Conservation Authority since shortly after the contamination was discovered. Cameco provided a full update to members of the CNSC at a significant development report hearing on September 13.
A small amount of uranium was found in an excavation under the UF6 production building on Friday, July 13, 2007. UF6 operations in the area near the excavation were immediately suspended and regulatory agencies notified. At that time, Cameco began an investigation to determine the source of the uranium and retained geotechnical experts to assist in ascertaining the source and scope of the situation. Drilling test wells and laboratory analysis began on Monday, July 16, 2007.
This situation developed over the course of the week following the July 13 discovery of a small amount of uranium in an excavation pit in the UF6 plant. Initially, Cameco believed that it was a very localized event. Nevertheless, Cameco reported the discovery to the CNSC, the Ontario Ministry of Environment and Environment Canada.
As the investigation got underway and information became available about groundwater quality under the UF6 plant, Cameco realized that it was a bigger issue than it originally thought, although the evidence continued to indicate that this was an onsite challenge for the company and not an issue of public health and safety.
On July 19, the company made the decision to suspend UF6 production for a minimum of two months to conduct an investigation and provide time to develop long-term environmental management plans. Cameco announced the discovery of uranium and production-related chemicals beneath the UF6 plant on July 20.
Cameco suspended UF6 production to provide time to fully investigate and resolve the situation. Cameco takes the discovery of soils containing uranium and production-related chemicals very seriously and want to ensure that we have a complete understanding of the situation before we resume production.
The soils are in a contained, subsurface area. All evidence to date indicates this situation poses no health or safety risk for employees or the public.
Groundwater is found at variable depths but tends to range from five to six metres.
On July 13, there were 13 groundwater monitoring wells in place at various locations on the site to monitor groundwater quality. Eight wells surrounded the UF6 production plant. Groundwater quality from these wells has traditionally been tested on a quarterly basis but Cameco has increased testing to monthly since the discovery. Results of the groundwater quality testing are included in the quarterly environmental status reports to the Municipality of Port Hope. Copies of past reports can be found at http://www.cameco.com/port_hope/environment/environment_status.php.
Since this discovery, more than 40 wells have been installed in and around the UF6 production plant.
"When rain falls to the ground, the water does not stop moving. Some of it flows along the surface to streams or lakes, some of it is used by plants, some evaporates and returns to the atmosphere, and some sinks into the ground. Imagine pouring a glass of water onto a pile of sand. Where does the water go? The water moves into the spaces between the particles of sand.
Groundwater is water that is found underground in the cracks and spaces in soil, sand and rock. Groundwater is stored in--and moves slowly through--layers of soil, sand and rocks called aquifers. Aquifers typically consist of gravel, sand, sandstone, or fractured rock, like limestone. These materials are permeable because they have large connected spaces that allow water to flow through. The speed at which groundwater flows depends on the size of the spaces in the soil or rock and how well the spaces are connected."
Source: The Groundwater Foundation
Officials from the Canadian Nuclear Safety Commission (CNSC) were notified of the initial discovery on Friday, July 13 and visited the Port Hope conversion facility on Thursday, July 19. An official from Ontario's Ministry of the Environment visited the site on July 13. Weekly inspections have been conducted by the CNSC throughout August and into September.
The CNSC has received regular updates from Cameco and these updates have also been provided to Environment Canada, the Ontario Ministry of Environment and the Ganaraska Region Conservation Authority.
Although Cameco made the decision to suspend UF6 production on its own initiative, the CNSC has informed the company that written approval from the regulator must be received before production can resume.
Uranium levels in some of the samples taken to date are higher than normal but other samples are consistent with normal low levels for the site. The identified and potential leak points carry solutions containing low levels of uranium.
Cameco monitors radiation levels at its facility and has not seen an increase in radiation exposures as a result of the discovery of these soils.
Cameco was installing a new tempered water tank for the cell room. This is considered a routine operation
Cameco is continuing to investigate the situation to ascertain the amount of soil that has been exposed to uranium and production-related chemicals.
Cameco is conducting an investigation to determine how the soils were exposed to uranium and production-related chemicals. By suspending UF6 production Cameco and its independent consultants have the opportunity to conduct a full and comprehensive investigation.
An environmental management plan to address this situation will be developed when Cameco and its consultants have completed the investigation and determined the exact characteristics and volume of the soils. The plan will be based on the best technical advice we receive from our independent experts. Based on the information gathered to date, Golder Associates is recommending that the contaminated groundwater be pumped and treated onsite. If any contaminated soil is removed, it would be safely stored by Cameco and addressed in an appropriate manner at the time of final decommissioning of the facility.
None of the contaminated material under building 50 will be transferred to the proposed long-term waste management facility on Baulch Road.
Cameco is unaware of any structural issues with the UF6 plant. Concrete experts from Golder Associates have not found any structural problems in the course of their investigation.
We do not have enough information to provide a definitive answer. We will continue to do everything possible to avoid layoffs but it may be impossible to avoid them.
We expect to have enough information by early November to estimate when UF6 production will resume and this will help us to determine the employment situation.